Period of limitation for claims for defects in rooftop photovoltaic installations

PrintMailRate-it

In a nutshell: 

According to a brand-new ruling of the seventh Senate of the German Federal Supreme Court [BGH], a photovoltaic installation erected on a building is part of that building, and thus, the period of limitation for claims for defects in such installations is five years, and not two years, which according to the ruling issued in 2013 by the eighth Senate of BGH was the applicable period of limitation.


However, there is only an apparent inconsistency in the opinions of the German Supreme Court on this contentious issue that frequently rivets the attention of the Higher Regional Courts [OLG] across all federal states. Crucial for the differences in the judgements are the facts and circumstances that the court takes as a basis in each case, more specifically, the question of whether the installation is a part of the building on whose rooftop it was built.



The question of when claims for defects in rooftop photovoltaic installations become time-barred has for years been the subject of various rulings issued by the Higher Regional Courts (OLGs) and, recently also even by the BGH. The large number of the rulings issued in this matter suggests that there is no single and clear answer to this question. Neither does the most recent judgement of the BGH mark any change, be it only because it is apparently in conflict with the ruling issued by it in 2013. The conflict between the judgements is only apparent because the facts and circumstances of the two cases differ considerably and should also be differently assessed from the legal perspective. Nevertheless, in my opinion, the new ruling of BGH of June 2016 leaves a lot of room for discussion, which means that it is not very easy to understand.

 

The answer depends first of all on whether the installation is an independent structure or a part of a structure or building. It is what determines the period of limitation for the defect claims.


According to consistent case law of the BGH, the five-year period of limitation applies if a structure, specifically a photovoltaic installation, has been fitted into a building and serves the building-related purposes. However, whereas the feature of being “firmly fitted into the building” is relatively easy to determine, it is much harder to assess whether the structure concerned serves the building-related purposes. And this is exactly the issue where the judgement of the seventh Senate of June 2016 seems to be needing some explanation.

 

 

 Figure 1:  legal basis

 (Click to enlarge)

The judgement was based on the following facts and circumstances: 1

The claimant contracted the defendant to mount a photovoltaic installation on the roof of the tennis hall owned by the claimant. The photovoltaic installation consists of 335 framed modules, 18 kg each. The modules were mounted on a supporting structure which was firmly fixed to the roof. The supporting structure and the modules had to be mounted in such a way that the weight of the installation would not impair the roof structure and the installation would be storm proof. In addition, the mounting components and the cable ductwork penetrations into the inside of the tennis hall had to be fitted into the roofing using a method that permanently prevents penetration by water. The defendant laid about 500 m of cable to e.g. connect the modules with the inverters installed inside the hall.  To this end, the defendant installed cable ducts leading to the inside of the hall. Then, the defendant laid power lines between the inverters and a meter distribution box located outside the hall. This required extensive digging work. The defendant also installed a control and steering system inside the hall and wired and programmed that system to the inverters and modules. The claimant claims that the output of the installation is too low and demands a 25% reduction in the net fee. The Higher Regional Court in Munich (i.e. a court of second instance) dismissed the claim on account of the lapse of the limitation period.

In view of the size of the installation and the complexity of its construction as well as the fact that its key components were installed inside the tennis hall, the seventh Senate assumed that the installation was permanently fixed to the tennis hall and could not be separated from it without considerable effort. This reasoning is fairly understandable and a question of individual assessment.
However, the seventh Senate has taken for granted that the installation also meets the second feature requirement, and has assumed that it serves the purpose of the building.

 

 

In the case law, the feature of “serving the purpose of the building” was confirmed when the installation served a function relevant to the building itself, when it could be assumed that at least part of the power was supplied to the tennis hall from the rooftop installation. This was exactly the reason that the eighth Senate of the BGH gave to substantiate its decision to apply the shorter period of limitation, which refers to structures that do not form a part of and do not serve the purpose of another structure or building. In the case examined by the eighth Senate, the installation was mounted on a barn roof and the power generated by that installation was fed into the public grid for a fee. According to the judge’s opinion “the solar installation served its own independent purpose because it was supposed to generate power and thus to be an additional source of income for the farmer S; the installation would also have met this purpose if it had been mounted on any other building. Therefore, the photovoltaic installation does not perform any function relevant to the building (barn) itself. It was mounted there only because the farmer considered this appropriate for his purposes”. The court goes on to hold that: “Even if a part of the power generated by the solar installation were used to supply power to the barn, this would not result, in the case of a dispute, in the applicability of the five-year period of limitation. This is because also then the main purpose of mounting the installation would be to create an additional source of income for the claimant, and therefore also in such a situation the installation would not serve the building-related purposes.” 


In its current ruling, the seventh Senate clearly does not share this opinion. In the seventh Senate’s opinion what is relevant is not whether the PV installation performs a function for the building, but only whether it serves the purpose of a fundamental renovation of the building. Thus, the feature of “serving the purpose of the building” has been interpreted entirely differently in this case. According to the seventh Senate, what counts is whether the mounting of the installation on the roof would have been classified as work on a structure or building if it had taken place during the construction of the hall. The seventh Senate answered this in the affirmative by presenting the following argument: “… since the building, regardless of its other purposes, would have also been used as a carrying structure for a photovoltaic installation anyway.” This should apply also in cases where the work carried out on the roof is equal to the construction of a new building. The mounting of the installation required major changes in the roof panel and the building structure, and therefore, in the opinion of the BGH, it must be seen as a fundamental renovation of the tennis hall.

 

This, however, is not convincing. The primary purpose of a tennis hall is to provide tennis courts to tennis players; it must also accommodate changing rooms, showers and possibly a food outlet. The mounting of a rooftop PV installation does not change the purpose of the tennis hall. The BGH infers, without giving any comprehensible reason and based solely on the fact that the mounting of the PV installation was a complex and a costly task, that the hall was constructed also for the purpose of operating a PV installation on its roof and, therefore, the mounting of a PV installation has extended the functions of the hall. If this line of case-law continues to apply in the future, it will have to be assumed that whenever the mounting of a PV installation on a roof requires comprehensive mounting work, this results in extending the functions of the roof in that the roof becomes a carrying structure for a PV installation.

 

 

Thus, the legal situation of owners and operators of rooftop photovoltaic installations is not much clearer than before the judgement. Therefore, we recommend that all those who accepted their installation maximally two years ago should check it for defects in time and file a claim for defects in court before the end of the two-year time limit.

 

The judgement of the BGH of 02 June 2016 has not yet shattered the hopes of all those who accepted the installation within the five-year period; what they have to do now is demonstrate to the court that the building underwent comprehensive changes and convince it that their case is comparable to that examined and decided by the seventh Senate.   



________________________

1 BGH Press Office Notification No. 95/2016 of 2 June 2016.

Newsletter

How we can help

Trendreport - growth countries renewable energy

The trendreport on renewable energies gives an overview of the opportunities and risks in selected fast-growing countries. Download

Online platform for renewable energy projects

Skip Ribbon Commands
Skip to main content
Deutschland Weltweit Search Menu